Tuesday, July 10, 2012

Dry Year Effects Crop Yeilds

Little snow pack and virtually no spring precipitation has left most farmers in a similar situation of not enough water to maximize crop yields. The situation has been complicated by unusual temperature extremes early on in the season with isolated incidences of frost damaged hay and cereal grain crops. The unseasonal heat the past few weeks has also taken its toll on corn and alfalfa yields. Some farmers are reporting up to 30% reduction in tonages harvested to date. With little relief in sight many people are deciding which crops to use their remaining water on to get the best return. This weather pattern is so different from last year in both water precipitation as well as temperature. All across the U.S. similar situations exist. Individual canal companies are evaluating the necessity of allocating additional stored water from the strawberry bank to supplement the low snow pack.

Monday, July 9, 2012

July Board Agenda


STRAWBERRY WATER USERS ASSOCIATION
Board of Director’s Meeting – Wednesday, July 11, 2012 7:00 p.m.
AGENDA
1.     Welcome and Introductions                                                                                7:00

2.     Approval of Minutes – June 13, 2012   

3.     POWER                                                                                                                     7:10

a.    Lobbyist Report
b.    Generation
c.    Spanish Fork Flow Control Structure Power Plant

4.     IRRIGATION COMMITTEE
                                                                                                                                    7:30
a.    River Commissioner’s Report
b.    Change of Place of Use Requests
c.    Signed Water Dedication Agreements (WDA)


a.        Reconsider Public Officials Bar B Que

5.     FINANCE & PERSONNEL COMMITTEE                                            7:50                                       
a.    Disbursements & Expenses
b.    Financial Reports & Investment
c.    Insurance Review

6.     WATER POLICIES COMMITTEE                                                                                    8:10

a.    Streamline Office Hourly Billing Rate
b.    Springville Irrigation exchange application

7.     PROPERTIES & DEVELOPMENT COMMITTEE                                            8:30   

a.    Maintenance & Water Conservation Projects – Status Report
b.    Large Warehouse Report
c.    Properties Report
a.        Nephi Property Proposal
d.    Friends of Strawberry – Kelly Lewis

8.     PUBLIC AFFAIRS                                                                                                   8:50

9.     EXECUTIVE COMMITTEE                                                                                               9:10

Sunday, July 1, 2012

June Board Minutes


STRAWBERRY WATER USERS ASSOCIATION
REGULAR MEETING OF THE BOARD OF DIRECTORS

June 13, 2012
The Strawberry Water Users Association Board of Directors held a regular board meeting in the Association’s office at Payson, Utah, Wednesday, June 13, 2012, at 7:00 p.m.
Thirteen directors were present with Dan Ellsworth, Scott Phillips and J. Merrill Hallam being absent.  Shawn Thomas was in attendance and recorded the minutes.
Vice President Quentin Francom conducted the meeting. Guy Larson offered the invocation and Quentin Francom led the group in the pledge of allegiance. Vice President Francom welcomed Debbie Vanoy from Central Utah Water Conservancy District and Alan Christensen with the Bureau of Reclamation to the meeting.
Approval of the Minutes 
Robert McMullin made a motion, seconded by Dale Rowley, approving the minutes of the regular board meeting held May 9, 2012.  It was unanimously approved.
Properties and Development Committee
Maintenance & Water Conservation Projects       Chairman Quentin Francom reported on the Maintenance & Water Conservation Projects and photos of the projects were shown.
Large Warehouse     Chairman Quentin Francom reported that Zion’s Bank came and moved the stuff they had rights to out of the warehouse. SWUA will try and sell the remaining inventory because Zion’s Bank signed it over to us. We will make attempts to sell the items leftover in the warehouse to make a partial payment on rent, repairs, and cleaning.  The construction foreman is getting bids for these items.
Small Warehouse     Kevin Anderson asked what is going on with Hathaway it appears they have more trucks here all the time I am concerned about damage to the asphalt. Are they being allowed to do more than what is in their agreement? Chairman Francom responded and reported that they are just about caught up on their rent.
Nephi Property          Chairman Francom reported that Greenline Equipment Group that was interested in SWUA’s Nephi property cancelled the meeting they had scheduled with us.
Chairman Francom suggested that we pursue selling the land.
Robert McMullin made a motion, seconded by Blair Hamilton, approving the General Manager discusses with realtor/agent listing the Nephi property and bring a proposal back to the board for review. It was unanimously approved.
Calvin Crandall arrived to the meeting at 7:18 p.m.
Vice President Francom turned the meeting over to President Crandall.
Other
Robert McMullin reported that individuals at IFA have had people approach them about possibly putting a rail head at the site near SWUA’s IFA property. Robert suggested the committee spend some time and research this.
Friends of Strawberry           Kelly Lewis reported on the Friends of Strawberry meeting.
Water Policy Committee
Footnote 6     Chairman Garry Brown gave an update on the status of footnote 6.
Old Fields      Chairman Brown reported that a meeting was held concerning old fields. SWUA’s council reinforced that it is our duty to represent the shareholders interest in the matter. The water will go back on the lots (this property previously known as Pages). SWUA has spent many hours on this project by staff. Caren Kirk will attempt to create a historical outline of the old fields and time spent by staff.
Finance Committee
Disbursements and Expenses
Kelly Lewis made a motion, seconded by Guy Larson, approving payment of the invoices, and checks previously written as presented.  It was unanimously approved.
Property & Liability Insurance Renewal Proposal Chairman Anderson reported that the Committee reviewed the proposals for SWUA’s property and liability insurance. The Committee recommends Arch’s proposal with a premium of $78,101 and Utah Workers Compensation Fund with a premium of $8,846
Robert McMullin made a motion, seconded by Kelly Lewis, approving the Arch premium of $78,101 and the $8,846 proposal from the Utah Workers Compensation Fund.  It was unanimously approved.
Financial Reports and Investments Chairman Kevin Anderson reported on SWUA’s investments.
Irrigation Committee
River Commissioner's Report           Chairman Jesse Warren reviewed the Spanish Fork River Commissioner’s written report that is maintained in SWUA’s files.  
Change of Place of Use and Water Deeds          
Robert McMullin made a motion, seconded by Guy Larson, approving:
1.    A Water Deed request made by Margaret J. Backus to Nicholas and Rachel Button Serial No. 624.014 for a total of 1.00 acre foot.
            It was unanimously approved.




Signed Water Dedication Agreements (WDA)     Were not discussed.
Other
Chairman Warren reported that the committee recommends not holding the public officials Bar B Que this fall due to budget issues.
Guy Larson made a motion, seconded by Kevin Anderson, approving that due to budget short falls this year’s Public Officials Bar B Que be cancelled.  It was approved with a vote of 8 in favor and 6 opposed.
Quentin Francom asked what SWUA’s fees are to administer the CUWCD rental water. Staff reviewed some of the fee’s we charge to administer this but to ensure we are giving accurate information I would have to get the breakdown to make sure I am covering all of the costs.
Robert McMullin recommended that the Water Policy committee review this matter and bring back a recommendation.
There was some discussion on canal company losses and delivery of the bank. The water policy committee will continue discussing these matters and bring it back to the board when they have a recommendation.
Power Committee
Lobbyist Report    Chairman Robert McMullin gave a status report on the lobbyist.

Generation     Chairman McMullin reported on the hydro generation for May 2012

Spanish Fork Flow Control Structure Power Plant (SFFCSPP) Chairman McMullin reported that we had a meeting with SESD and CUWCD to discuss the SFFCSPP.  There were three items on the agenda for discussion 1. Optimal location; 2. Optimal sizing; 3. Confirm and refine project financing. It was determined to proceed with these three items would cost approximately $15,000. Our committee determined that we would like to proceed our share would be $5,000.

Quentin Francom made a motion, seconded by Kelly Lewis, approving the funds up to $5,000 to proceed with this phase of the Spanish Fork Flow Control Structure Power Plant engineering.  It was unanimously approved.
Other

Spanish Fork City Dam        Chairman McMullin recently attended a meeting concerning the City Dam after engineering was done it was determined that it is not practical to generate power at the location of the new dam.  SWUA paid $4,000 to have engineering done for a determination on generation.

Public Affairs Committee No report.
Executive Committee        No report.
Other Business                  
Blair Hamilton indicated that Fred Vincent and Wayne Peterson have requested a reduced rate from SESD on a pump that has a demand meter that they will be using. Blair asked if SWUA is willing to reduce their rate. Blair asked if Spanish Fork Southeast Irrigation Company could possible use rehabilitation funds for this.
Garry Brown asked who will be using the water that is pumped. Blair indicated that Spanish Fork City will use the water. Maybe, possibly Spanish Fork Southeast Irrigation Company.
There was much discussion about this issue. Many felt that if you do this for some you need to do it for all.
Recharge Project
Alan Christensen discussed the Spring Creek recharge project and indicated that SWUA may want to become familiar with it.
Garry Brown was directed to check with Jay Franson about this project.
There being no further business, the meeting adjourned at 8:55 pm.

Wednesday, May 9, 2012

Rehabilitation Continues

River Commisioner Information


Dear Watermasters & Schedulers,
What a difference a year makes! From feast to famine.
I figured that an update letter would be good to catch everyone up, and to touch bases with you on our schedule and procedures.
First, Strawberry Water was first delivered on April 23, 2012. This is one of the earliest delivery dates in recent history. Central Utah Water Conservancy District has been working on the Sleeve Valves in Sixth Water since October of 2011. Many problems were encountered and the valves that were removed are still not operational at this time. One valve is in place and should be available for service this week. In the mean time, water is being delivered from the old Strawberry Tunnel. Delivery from the Strawberry Tunnel is restricted to 200 cfs. Today, May 1, 2012 we are delivering 160 cfs. One Sleeve Valve will deliver at least 350 cfs. It is anticipated that we will be able to deliver over 500 cfs combined between the old Strawberry Tunnel and one Sleeve Valve at Sixth Water this irrigation year and we will be in good shape. However, until the Sleeve Valve is in and operational, we are in a bit of a pickle. Hopefully that will change by this weekend.
Our storage in Strawberry Reservoir is absolutely full. We have a full 61,000 acre foot allotment, and a full 50,000 acre foot “Bank”. The “Bank” is to allow us to save water in times of plenty and then be able to utilize that water in times of shortage. It makes sense to use some of the banked water this year.
Also, Central Utah Water Conservancy District has made it known that those that have leased CUP water will be able to draw as much as 20% more water than their contracted amount, this year only.
These factors should help with an upcoming difficult year. As usual, please be vigilant in managing the water in your canal company. Let your appropriators know of the lack of natural flow in the river systems this year and encourage them to plan accordingly. Maintaining ditches and head gates to conserve water is critical.

May Board Agenda


STRAWBERRY WATER USERS ASSOCIATION
Board of Director’s Meeting – Wednesday, May 9, 2012 7:00 p.m.
AGENDA
1.     Welcome and Introductions                                                                                7:00

2.     Approval of Minutes – April 11, 2012    

3.     POWER COMMITTEE                                                                                           7:10

a.    Lobbyist Report
b.    Generation
c.    Interconnect Agreement UAMPS

4.     IRRIGATION COMMITTEE
                                                                                                                                    7:30
a.    River Commissioner’s Report
b.    Change of Place of Use Requests
c.    Signed Water Dedication Agreements (WDA)

5.     FINANCE & PERSONNEL COMMITTEE                                                          7:50                                       
a.    Disbursements & Expenses
b.    Financial Reports & Investment

6.     WATER POLICIES COMMITTEE                                                                                    8:10

a.    Highline Canal Notice of Intent to enclose canal

7.     PROPERTIES & DEVELOPMENT COMMITTEE                                            8:30   

a.    Maintenance & Water Conservation Projects – Status Report
b.    Large Warehouse Report
c.    Friends of Strawberry – Kelly Lewis

8.     PUBLIC AFFAIRS                                                                                                   8:50

9.     EXECUTIVE COMMITTEE                                                                                               9:10

10.  OTHER BUSINESS                                                                                                            9:20

April Board Minutes


STRAWBERRY WATER USERS ASSOCIATION
REGULAR MEETING OF THE BOARD OF DIRECTORS

 April 11, 2012
The Strawberry Water Users Association Board of Directors held a regular board meeting in the Association’s office at Payson, Utah, Wednesday, April 11, 2012, at 7:00 p.m.
Twelve directors were present with J. Merrill Hallam, Dan Ellsworth, Guy Larson, Scott Phillips being absent.  Jeremy Sorensen, and Shawn Thomas were in attendance.   Shawn Thomas recorded the minutes.
President Calvin Crandall conducted the meeting. Robert McMullin offered the invocation and Neil Sorensen led the group in the pledge of allegiance. President Crandall welcomed Neil Sorensen back and welcomed Jackson Crofts, Darrell Devy and Debbie Vanoy from Central Utah Water Conservancy District to the meeting also Trapper Burdick with Spanish Fork City
Approval of the Minutes 
Dale Rowley made a motion, seconded by Robert McMullin, approving the minutes of the regular board meeting held March 6, 2012.  It was unanimously approved.
CUWCD annual reprt on Diamond Fork System       Jackson Crofts and Darrell Devy reported on the status of repairs and improvements being made in the Diamond Fork System.
Jackson Crofts and Darrell Devy excused themselves from the meeting at 8:00 p.m.
Properties and Development Committee
Spanish Fork City Construction Access request              Trapper Burdick with Spanish Fork City reported on the work currently being done through the Spanish Fork Diversion Dam property it should be complete within 30 to 45 days.  Spanish Fork City is requesting additional access from SWUA for their stream bank stabilization project near the diversion dam.
Blair Hamilton made a motion, seconded by Robert McMullin, approving access to Spanish Fork City for their stream bank stabilization project. It was unanimously approved.
Trapper excused himself from the meeting at 8:07 p.m.
Other   Chairman Quentin Francom reported that the committee recommends a new block retaining wall at the diversion dam. The diversion dam employees would complete the labor on the wall during their normal working hours. The recommendation is to have the wall complete before the new asphalt is done.
Quentin Francom made a motion, seconded by Neil Sorensen, approving $7,500 to purchase block for a retaining wall at the diversion dam. The motion failed.
There was discussion with the board that the committee should look at all options for the retaining wall including finding funding for the block.
Maintenance & Water Conservation Projects       Chairman Quentin Francom reported on the Maintenance & Water Conservation Projects and photos of the projects were shown.
Large Warehouse     Chairman Quentin Francom asked if the board wants to pursue a judgment bond against Bella Granite.
Quentin Francom made a motion, seconded by Robert McMullin, approving SWUA pursue a judgment against Bella Granite. It was unanimously approved.
Zion’s bank is temporarily paying the rent on the warehouse while they deal with Bella Granite’s inventory.
Robert McMullin suggested you get the cost from the attorney to file a judgment.
Other   Chairman Francom reported that staff has received bids to trim the tree’s at the Spanish Fork Power Plant.
Quentin Francom made a motion, seconded by Jesse Warren, approving the bid for $2,800 to trim the tree’s at the Spanish Fork Power Plant. It was unanimously approved.
Diamond Fork Gauging Station      Chairman Francom reported that Jeremy Sorensen had an appointment with Reed Murray to discuss the proposed Diamond Fork Gauging station. During the meeting it was determined that the project would be approved.
Friends of Strawberry           Kelly Lewis reported on the Friends of Strawberry meeting.
Water Policy Committee
BOR policy update (Footnote 6 changes)  Chairman Garry Brown reported that SWUA has submitted comments on footnote 6. If you would like a copy talk to Jeremy.
Other   Chairman Brown reported that Jeremy met with SUVMWA’s engineer and discussed ground water recharge.
Chairman Brown reported that Jeremy has been in discussions with Payson City concerning the Old Fields water exchange. Jeremy spoke with Shawn Draney about this and Shawn suggested that Payson City/Strawberry High Line Canal Company and SWUA meet and discuss this issue so that everyone understands what is being requested and how to accomplish the task so that it will work for everyone.
Chairman Brown reported that a meeting was held recently to discuss creating a Water District in south Utah County. Jeremy attended the meeting.
Chairman Brown reminded everyone about the Canal Companies Coalition meeting tomorrow night.
Finance Committee
Disbursements and Expenses
Garry Brown made a motion, seconded by Robert McMullin, approving payment of the invoices, and checks previously written as presented.  It was unanimously approved.
Financial Reports and Investments Chairman Kevin Anderson reported that we received a check for $6,400 from DBSI. SWUA’s ownership has been increased in Highlands at Spectrum we should receive a check in August for approximately $10,000. The committee is still working with Colton.
Resolution for change in signers with financial services.
Kelly Lewis made a motion, seconded by Blair Hamilton, approving the SWUA President, Vice-President, Finance Committee chairman and the Secretary/Treasurer become signers on all financial services, and to create a corporate resolution if needed.  It was unanimously approved.
Irrigation Committee
River Commissioner's Report           Chairman Jesse Warren reviewed the Spanish Fork River Commissioner’s written report that is maintained in SWUA’s files.  
Change of Place of Use and Water Deeds          
Garry Brown made a motion, seconded by Robert McMullin, approving:
1.    A Water Deed request made by Blake and Sara Ross to Richard Behling Serial No. 337.080 for a total of .65 acre feet.
2.    A Water Deed request made by Nebo School District to LDS Church Serial No. 3517.002 for a total of 4.68 acre feet.
            It was unanimously approved.
Signed Water Dedication Agreements (WDA)
There were forty eight Water Dedication Agreements presented to be ratified by the board:
·        48 from Payson City/Strawberry High Line Canal Company for a combined total of 39.80 acre feet
  A listing of these agreements will be kept in the SWUA files.
Blair Hamilton made a motion, seconded by Neil Sorensen, to ratify the Water Dedication Agreements presented to the board.  It was unanimously approved.
Assessments             Chairman Warren reported that it has been suggested that delinquent CUP contracts be cancelled and that the outstanding balance be sent to collections.
Quentin Francom made a motion, seconded by Neil Sorensen, approving the CUP contracts that are currently delinquent be cancelled and the balance owing be sent for collections.  It was unanimously approved.
Other
Chairman Warren reported that the Utah Water Users Workshop meetings were very beneficial this year. J. Merrill Hallam was awarded the Outstanding Water Users at the banquet.
Power Committee
Other   Vice Chairman Neil Sorensen reported that the Payson Power Plant is back on line. The cost for repairs was approximately $6,000.

Lobbyist Report  Chairman Sorensen reported current activities with Bill Simmons.

It has been suggested that SWUA send two people to Washington, D.C. to testify on behalf of SWUA inn a hearing dealing with upstream costs on Diamond Fork.

Neil Sorensen made a motion, seconded by Kevin Anderson, approving the funds to send Calvin Crandall and Jeremy Sorensen to Washington, D.C. to testify at a hearing dealing with Diamond Fork.  It was unanimously approved.
Other   Chairman Sorensen reported that meetings have begun on the lease of power privilege between CUWCD/SESD and SWUA.

Public Affairs Committee No report.     
Executive Committee        No report.
Other Business                  
President Calvin Crandall reported that Debbie Vanoy with CUWCD will be attending our monthly board meetings.  Debbie was excused from the meeting at 9:17 p.m.
President Crandall discussed the board’s actions and responsibilities.
President Crandall reported that Taffy Peterson’s last day is this Friday.
Adjournment
There being no further business, the meeting adjourned at 9:25 pm.